Future Algona transfer station faces planning stage headwinds

South King County’s new recycling and transfer station is expected to be completed in 2026.

Opened in the mid-1960s, the Algona Transfer Station is at the end of its engineered lifespan. The outdated and undersized station lacks numerous features that newer facilities have, officials said. COURTESY PHOTO

Opened in the mid-1960s, the Algona Transfer Station is at the end of its engineered lifespan. The outdated and undersized station lacks numerous features that newer facilities have, officials said. COURTESY PHOTO

The original estimate for King County’s new recycling and transfer station called for it to begin operations in 2023 as the replacement for the aging, outmoded 56-year-old facility in Algona.

County officials say the future station at 35101 W. Valley Highway S., just north of the present one, will offer services its predecessor cannot, among them recycling, yard waste and household hazardous waste disposal. The new site is intended to make services more accessible and convenient for South King County residents.

But a recent glance at the King County Solid Waste Division website offers a revised completion date of 2026 — and, county officials say, even that may change.

Is there a problem? No, say county officials.

The first thing that happened, according to county officials, was that it took longer for the transfer station project to gain its conditional use permit from the city of Algona than it had expected.

“What had been estimated to be about an 8-month process took about 16 months,” Project Manager Karen Herndon, who was appointed to the position in July 2020, told the Reporter recently. “Between July of 2020 and September of 2021, we were waiting for that conditional use permit, and we finally got it in September of 2021.”

Calls to Algona Mayor Dave Hill were not returned as of press time.

The second thing that happened was that, while King County Solid Waste based its estimated 28-month construction window on other recent transfer station construction time frames, this past September, a consultant it had hired to perform professional scheduling services revised the schedule to 39 months.

“That’s a really significant gap that we’re working on right now to close and to research,” Herndon said. “We actually are taking another deep dive on the construction duration. But for the purposes of telling everyone in Solid Waste, King County and the public what our delivery date looks like, we were forced to go with that longer duration because of what the professional scheduling service told us.”

Herndon noted that, while KCSW’s own experts remain skeptical about the 39 months it will take to complete the transfer station, the county can’t approve the 28-month time frame, either.

“So, the conditional use permit duration, plus the revised estimate of construction duration, took the project from a delivery date of mid-2024 to a delivery of early 2026,” Herndon said, noting the timeline gradually slipped to 2026 over the course of the last 18 months.

King County operates eight transfer stations, two drop-boxes, the Cedar Hills Regional Landfill and many programs to help customers recycle.

King County’s Solid Waste Division chose the site after a multi-year siting and environmental review process.

Additional information about the Algona Transfer Station project, including opportunities to stay informed and engaged, is available online, or by contacting King County’s Solid Waste Division.


Talk to us

Please share your story tips by emailing editor@kentreporter.com.

To share your opinion for publication, submit a letter through our website https://www.kentreporter.com/submit-letter/. Include your name, address and daytime phone number. (We’ll only publish your name and hometown.) Please keep letters to 300 words or less.

This rendering depicts the future transfer station in Algona from the air. Courtesy King County Solid Waste

This rendering depicts the future transfer station in Algona from the air. Courtesy King County Solid Waste

A rendering of the future South King County Transfer Station in Algona. Courtesy King County Solid Waste Division.

This rendering depicts the future transfer station in Algona from the air. Courtesy King County Solid Waste

More in News

Crews on the SR 509 Completion Project in south King County install the framework for a new bus stop on SR 516, also known as Kent-Des Moines Road. The SR 509 Completion Project includes new or improved connections to existing transit centers and stops. COURTESY PHOTO, WSDOT
Eastbound SR 516 ramp to I-5 in Kent to close for 4 months

Drivers heading to northbound I-5 will use a temporary left turn lane

Courtesy Photo, King County
Tacoma boy, 17, charged with murder in November 2024 Kent case

Reportedly fired six shots into vehicle that killed 21-year-old SeaTac man on West Hill

t
CW series ‘Police 24/7’ features Kent indecent exposure case

Department also part of future TV episodes after crews responded on calls with police in 2024

t
Kent mobile home park fire displaces 7 people, kills family dog

Cause of accidental fire Feb. 6 in 24400 block of 64th Avenue S. remains under investigation

File Photo
Police arrest man at Kent hotel wanted for Alabama murder

Officers take fugitive into custody Feb. 5 for December 2024 shooting

Courtesy Photo, Kent School District
Seven candidates to interview for Kent School Board vacancy

School Board members scheduled to select replacement at Tuesday night, Feb. 11 special meeting

t
Kent man, 24, identified in city’s first homicide of 2025

Elijah J. Oceguera Bestgen fatally shot Feb. 7 in wooded area along Lake Fenwick Road South

t
Cancer Center is open and ready to serve South King County

Cancer patients can now receive treatment at the Valley Medical Center in Renton.

t
Kent officers part of CW ‘Police 24/7’ episode Thursday night, Feb. 6

Department also part of future episodes after CW crews responded on calls with police in 2024

An Amtrak train in Kent. FILE PHOTO, STEVE HUNTER, Kent Reporter
Pedestrian, 30, dies in Kent collision with Amtrak train | Update

Medical examiner identifies Kent man struck Wednesday evening, Feb. 5 near East Titus Street

t
NTSB rules pilot lost control in 2023 Kent small plane crash

Pilot and passenger were injured; pilot flew without receiving training in plane model’s operation

Courtesy Photo, King County
Man receives 35-year sentence for 2021 Kent killing of mother

Duane Bates borrowed pipe wrench from neighbor in beating death and later returned it