Federal Way Link Extension design-build contract over 25% complete

Sound Transit aiming for mid-2021 finish of design-build contract.

The design-build contact for the Federal Way Link Extension is more than 25% complete, according to Sound Transit.

Final design for the 7.8-mile, $3.1 billion route is scheduled to be completed by middle of this year. Utility and site preparation work began in 2019, followed by the start of heavy construction in July 2020.

“Community members across the region can watch the rapid construction progress that is now underway and look forward to 2024, when they can ride a light rail network that we’re on track to nearly triple, from 22 to 62 miles,” said Sound Transit CEO Peter Rogoff in a Feb. 10 news release. “These projects and the voter-approved projects that will follow will be critical both for our mobility and for creating thousands of jobs to help us rebound from the pandemic recession.”

Rogoff added that seven of the eight major Sound Transit extension projects under construction are on or below budget, and on or ahead of schedule.

So far, 30 of 121 drilled shafts for constructing elevated guideway and station facilities have been completed for the SeaTac to Federal Way extension scheduled to open in 2024. Work is also underway for the three new light rail stations and parking garages, adding 2,000 new parking spaces for riders. The stations and parking garages will be in Kent/Des Moines along Pacific Highway South, at South 272nd Street in Kent near Interstate 5 and in Federal Way.

Sound Transit’s Federal Way Link Extension extends from Angle Lake Station in SeaTac to an incoming light rail station next to the Federal Way Transit Center, later to venture into Pierce County via the Tacoma Dome Link Extension.


Talk to us

Please share your story tips by emailing editor@kentreporter.com.

To share your opinion for publication, submit a letter through our website https://www.kentreporter.com/submit-letter/. Include your name, address and daytime phone number. (We’ll only publish your name and hometown.) Please keep letters to 300 words or less.

Construction at the Kent/Des Moines Station, part of the Federal Way Link Extension. COURTESY PHOTO, Sound Transit

Construction at the Kent/Des Moines Station, part of the Federal Way Link Extension. COURTESY PHOTO, Sound Transit

More in News

King County Councilmember Steffanie Fain, left, Kent Mayor Dana Ralph and King County Councilmember Sarah Perry meet Dec. 12 along the Green River in Tukwila. COURTESY PHOTO, King County
Flooding continues to impact city of Kent Saturday, Dec. 13

Christmas Rush run/walk cancelled; another street closed; elected officials meet

t
Kent closes section of another street due to flooding

Portion of 78th Avenue South shut down; Christmas Rush run/walk remains on for Dec. 13

tt
Fincher’s farewell to Kent City Council after 12 years

‘We have to make sure that our people know we care for them,’ Brenda Fincher says

File Photo, Kent Reporter
Kent Police arrest man for DUI passed out in vehicle in road

911 caller reports car stopped in roadway with engine running along 88th Avenue South

t
Kent closes portions of two more streets due to water over roadway

124th Avenue SE and SE 256th Street added to list; long section of West Valley Highway still closed

t
Community celebrates new local light rail stations in Kent| Photos

Sound Transit opens stations at Kent Des Moines, Star Lake in Kent and Federal Way

Washington state Gov. Bob Ferguson announced a state of emergency Dec. 10 over the flooding. Courtesy photo
Gov. Ferguson declares statewide emergency over major flooding

The flooding has affected SR 410 both near Greenwater and Sumner.

t
City of Kent closes portion of West Valley Highway due to flooding

Shut down between Frager Road and South 277th Street; three other streets also closed

File Photo, Kent Reporter
Kent Police officer fires gun at suspect but man not hit

Sexual assault suspect taken into custody after nearly 3-hour incident Dec. 10 at Indigo Springs Apartments

Kent School Board directors Teresa Gregory (top left), Tim Clark and Donald Cook during a Dec. 3 work session with staff about the Kent School District’s budget. VIDEO SCREENSHOT, Kent School District
Kent School Board seeks budget cut details from district staff

Wants break down of $7 million in reductions from this year’s budget; student enrollment decline to continue

Maleng Regional Justice Center in Kent. FILE PHOTO, Kent Reporter
Judge sentences man, 40, for 2021 Kent drive-by shooting

Receives nearly 5 years in prison; shots fired at two people in vehicle for lack of drug payment

t
Motorcyclist recovering after Kent hit-and-run on East Hill

Galen Morris injured after hosting karaoke at Kent bar; friends start fundraiser